StocksMedium•23 November 2026•
4 min read

Downer wins A$1.1 billion Australian electricity transmission contract

By

Key Facts

1Downer won a contract worth about A$1.1 billion on 23 November 2026, with a 3-year construction period.
2The contract includes construction of about 110 kilometres of 500-kilovolt transmission lines.
3Downer shares rose 3.6% to A$7.20 at 10:19 a.m. AEDT on 23 November.
4Planning, design and procurement activities are expected to begin in December 2026, with field mobilisation in 2027, subject to final approvals.

Downer EDI said on 23 November 2026 that it had won a contract worth about A$1.1 billion to carry out electricity transmission line works for the Hunter Transmission project in New South Wales, over a 3-year construction period. The company said it would work with Transgrid for Energy Corporation of NSW. The contract places the company among efforts to expand the state’s electricity grid, while a market snapshot in the same session showed Downer shares higher. Market Index reported at 10:19 a.m. AEDT that the stock had risen 3.6% to A$7.20, among the biggest gainers on the ASX 200. These figures reflect the share price at that point in the session and do not represent the closing price.

The contract covers construction of about 110 kilometres of new 500-kilovolt double-circuit transmission lines, with lattice steel structures. The route runs between the Bayswater South and Olney substations, according to Downer’s statement. Transgrid says the project also includes two new substations at the sites and modifications to existing lines. The works form part of the transmission infrastructure needed to connect new electricity sources to the grid. The high-voltage lines are intended to carry power from generation areas to homes and businesses in New South Wales.

Downer said the project would strengthen the grid’s capacity to accommodate large-scale renewable energy, ease grid bottlenecks and support the replacement of coal-fired power stations that have reached the end of their operating lives. EnergyCo said the connection would deliver new electricity and storage from the Central-West Orana and New England renewable energy zones to homes and businesses in the state as older coal-fired power stations retire. That places the contract in the context of grid investments tied to a changing generation mix. The company did not specify the contract’s contribution to earnings or revenue in its win announcement. It also did not attribute the stock’s market move to a specific cause.

Downer described the contract arrangements as combining lump-sum components with variable mechanisms to address key uncertainties. It said the structure reduces execution risks compared with a traditional fixed-price model. This description reflects the nature of the contract and how some project risks are allocated, without disclosing a specific financial impact on the company’s results. Chief Executive Peter Tompkins said the win “strengthens Downer’s position in the fast-growing electricity transmission infrastructure market and supports the growth strategy for its energy and utilities business.” The company added that the project gives it an opportunity to compete for other work in Australia’s multi-year transmission investment pipeline.

EnergyCo said the contract followed a procurement process overseen by the Australian Energy Regulator. The project received state planning approval in July 2026, subject to 115 conditions covering environmental protection, management of construction impacts, support for landowners and community engagement. EnergyCo said about 90% of the project corridor runs through mining and energy land or government land. The final route affects fewer than 20 private properties, compared with 70 properties on the initial corridor. The agency also expects the project to provide 900 jobs during construction, while about 700 local residents are already working in construction and specialist trades in the Hunter-Central Coast region.

Planning, design and procurement activities are scheduled to begin in December 2026, with field mobilisation to start during 2027, subject to final approvals, Downer said. Transgrid said the project had moved into detailed design, planning and management work following its receipt of planning approvals from New South Wales and the Commonwealth. Construction remains conditional on completing detailed design, management plans and pre-construction requirements. EnergyCo is targeting construction to begin in early 2027 and project completion in 2029, describing the timetable as indicative and subject to approvals. The agency estimates the project will support about 1,500 jobs at peak construction, including more than 780 jobs in the Hunter region.