StocksMedium•22 November 2026•
5 min read

Sunshine report estimates 264 million ounces of silver resources, but no reserves

By

Key Facts

1Total resources across 36 veins amount to 263.762 million ounces of silver.
2The estimate includes 103.915 million ounces of indicated resources and 159.847 million ounces of inferred resources.
3The report estimates no mineral reserves for the Sunshine mine.
4The company expects an updated resource estimate in the first quarter of 2027 and a feasibility study in the second quarter.
5The company plans to return to production in late 2028.

An independent technical report prepared by Sunshine Silver Mining & Refining estimated resources at its Sunshine mine in Idaho at about 263.762 million ounces of silver, a figure close to 264 million and representing total resources across 36 mineralized veins. The estimate is from a technical summary report under S-K 1300 dated March 25, 2026, while the resource estimate is effective as of February 24 of the same year. The report classifies 103.915 million ounces as indicated resources, compared with 159.847 million ounces as inferred resources. The report estimates no mineral reserves for the mine, so the resource figure is not equivalent to a confirmed quantity that can be commercially extracted. The estimate comes as the company advances drilling and mine development ahead of a feasibility study and a planned restart.

The average silver grade for indicated resources is 29.8 ounces per short ton, while the grade for inferred resources is 22.6 ounces per short ton, according to the report. Inferred resources exceed indicated resources in size, making resource classification essential to interpreting the total figure, rather than treating it as a simple sum of ounces. The report cautions that its economic analyses are preliminary and rely in part on inferred resources, whose level of certainty is insufficient for classification as mineral reserves. As a result, the production and feasibility estimates in the report remain tied to an initial evaluation stage. The report presents a base-case scenario that assumes a 36-month pre-production period, followed by a mine life of 24 years.

Under the base-case scenario, the company expects average annual production of about 6.7 million ounces of silver during the first five years of production, followed by an average of about 5.8 million ounces annually over the mine's 24-year life. The study estimates initial capital at about $286.9 million, to be spent over three years, in addition to $560.2 million in sustaining capital over the mine's life. These figures reflect the project scope assumed in the technical evaluation, but remain part of a preliminary economic analysis that relies in part on inferred resources. The report did not estimate mineral reserves that could provide a basis for treating these quantities as a confirmed production plan. The company is targeting completion of the mine's feasibility study in the second quarter of 2027, according to its operating update filed with the U.S. Securities and Exchange Commission.

The company announced on November 5, 2026, that it had completed an underground drilling program totaling about 51,250 meters across 218 holes. It said the results will be incorporated into an updated resource estimate it expects to issue in the first quarter of 2027, with that estimate set to form the basis for the feasibility study targeted for the second quarter. Among the results highlighted by the company was a 1.00-meter intercept in the NY Boy vein grading 7,069 grams of silver per ton, including a 0.58-meter interval grading 12,103 grams per ton. It said the drilling program was designed to support upgrading resource classifications in areas underpinning the mine's initial plan, as well as to assess near-mine expansion opportunities in the Upper Country area. This work provides inputs for the next estimate, which could change the distribution of resources among categories, but the announced timing remains the first quarter of 2027.

An earlier update said the company had completed about 47,600 meters of underground drilling through September 30, 2026, and expected to report further results from drilling toward the mine's depth before year-end. It also completed about 1,835 meters of underground access expansion work during the first nine months of 2026, including about 670 meters in the third quarter. In September, the company expanded its mineral rights by about 14,100 acres, or 60%, to nearly 38,000 acres, and announced a multi-year surface exploration program covering about 45,000 meters across the expanded land package. In its second-quarter update, it said it had $288.7 million in cash and equivalents at the end of June 2026, enabling it to fund feasibility studies, drilling, underground development and infrastructure improvements. The company is targeting a return to production at the Sunshine mine in late 2028, following the resource update expected in the first quarter and the feasibility study targeted for the second quarter of 2027.

EL7 data showed that SSMR shares closed at $10.45 in the November 20, 2026, session. That is the recorded closing price for the session and, on its own, does not provide evidence of the resource estimate's effect on trading. The technical estimate itself is dated March and effective from February, while the announcement that the drilling program was complete came in November. This sequence places the resource update expected in the first quarter of 2027 among the company's next announced steps. The company then targets completion of the feasibility study in the second quarter, with a return to production still planned for late 2028.