Anduril Invests $3.7 Billion in Maryland Plant for Virginia Submarine Components

By

Key Facts

1Anduril’s private investment in Arsenal-2 is $3.7 billion and was announced on October 6, 2026.
2The U.S. Navy contract is worth up to $2.9 billion, and its payments are tied to demonstrated production results.
3The project could add about 9 million production hours a year, or nearly 15% to production capacity for the Virginia-class program once operational.
4The company targets initial operations by 2030, after construction is targeted to begin in early 2027.
5A Reuters report projected 3,100 direct jobs and more than 11,000 indirect jobs when the plant is operating.

Anduril announced on October 6, 2026, a private investment of $3.7 billion to build the Arsenal-2 facility at Sparrows Point, Maryland, to manufacture large components and assemblies for nuclear-powered Virginia-class attack submarines. The company said the facility will meet submarine shipyards’ needs for complex parts, while Reuters reported that the U.S. Navy awarded it a separate contract worth up to $2.9 billion. Contract payments are tied to demonstrated production results, linking government funding to what the facility actually produces. The investment and contract together are worth up to $6.6 billion, according to Reuters. An earlier EL7 report on October 6 covered the contract and investment as linked plans to expand submarine-component production.

The project is located in Baltimore County, and Anduril describes the planned facility as a two-million-square-foot manufacturing space. Arsenal-2 will send large components and assemblies to Electric Boat and Newport News Shipbuilding for final submarine assembly. This role places the plant in the existing supply chain as a supplier of the parts and assemblies required by the main shipyards. Required components include precision torpedo tubes and propulsion tanks, according to Defense One, citing a vice admiral responsible for submarine construction. The official said the shipyards need these components now, while Anduril has defined the plant’s scope as Virginia-class submarine components and assemblies.

According to a Navy official cited by Defense One, the project could add about 9 million production hours a year, equivalent to an increase of nearly 15% in production capacity for the Virginia-class program once the facility is operating. Both estimates refer to additional annual production capacity for the industrial base, not the number of completed submarines or hours already worked. This comes as The Washington Post reported that shipyards were delivering about 1.1 submarines of the class a year under the conditions described in its report published on October 6, 2026, below the military’s target of two submarines a year. The U.S. Government Accountability Office also found that shipyards were operating at a pace of one submarine a year in June 2025, half the Navy’s target. The office said the Navy received two submarines of the class in 2025, but delivery of each was delayed by more than 3 years.

Anduril set the start of construction for early 2027, with initial operations targeted by 2030. The company said the $3.7 billion investment will cover facility outfitting, workforce development and the technologies and capabilities needed at the site. Reuters reported that the plant is expected to begin operations by the end of the decade and provide 3,100 direct jobs while supporting more than 11,000 indirect jobs. The company has set a target of more than 3,100 direct jobs by 2034, while the project is expected, according to its estimate, to generate $2 billion in annual economic output. President Donald Trump said U.S. taxpayers would receive a 40% stake in the new subsidiary that will operate the shipyard; Anduril clarified that the stake is not in the parent company itself.

The project reuses the Sparrows Point site, which housed a Bethlehem Steel plant before it closed in 2012, according to the Associated Press. The expansion comes as submarine shipyards face bottlenecks in materials and labor; the Government Accountability Office attributed slow construction to late material deliveries from suppliers and limited availability of experienced workers amid labor-market competition. The office reported that the Navy incurred about $4.2 billion in operating and support costs during 2025 for attack submarines awaiting entry into maintenance shipyards or delayed in completing maintenance. The Associated Press estimated that the Navy had 26 Virginia-class submarines in its report published on October 6, 2026, and expected two submarines to be added to the fleet the following spring. Anduril’s plant aims to expand component supplies within the submarine production process, while initial operations remain targeted by 2030.