Unanimous Approval Clears Way to Add 950 Billion Cubic Feet a Year to Gas Exports
Key Facts
The Federal Energy Regulatory Commission unanimously approved the expansion of the Sabine Pass liquefied natural gas facility in Cameron Parish, Louisiana, at its open meeting on November 19, 2026. The decision authorizes the construction and operation of three additional liquefaction units, along with an expansion of the Creole Trail pipeline and construction of the Sabine Crossing pipeline to serve the terminal. The commission estimated the project would add 950 billion cubic feet a year to natural gas export capacity, bringing estimated total capacity to 2,611.9 billion cubic feet a year. Commission Chair Laura Swett said the agency was “again delivering” on its commitment to ensure affordable and reliable natural gas supplies for Americans. The approval is a major regulatory step for the project, but on its own it does not mean Cheniere has made a final investment decision.
The expansion aims to increase the capacity of the Sabine Pass facility by about 20 million metric tons a year through three production trains, according to a Reuters report. The terminal currently operates six liquefaction units, with total nameplate capacity of about 30 million tons a year, according to Cheniere. The plan includes Trains 7, 8 and 9, with each new unit having maximum capacity of about 300 billion cubic feet a year. The project also includes a boil-off gas reliquefaction unit with additional capacity of 50 billion cubic feet a year. Cheniere has divided construction into two phases: the first includes Train 7 and the reliquefaction unit, while the second includes Trains 8 and 9. This places the proposed project on top of an existing operating base, with the additional units being brought online in stages.
The infrastructure includes the Sabine Crossing pipeline, about 55.6 miles long and 48 inches in diameter, designed to transport 2.7 billion cubic feet a day to the terminal. The expansion of the Creole Trail system is expected to add transportation capacity of 0.9 billion cubic feet a day. These pipelines connect the terminal to the gas sources needed to supply the new liquefaction units as part of the project approved by the commission. The commission also estimated that LNG carrier traffic in the Gulf of America and the Sabine Pass channel would rise from 580 to 740 vessels a year. The expected increase is 160 vessels a year after the expansion, according to the environmental impact assessment estimates. The project’s effects therefore include both gas transportation to the terminal and the maritime shipping activity associated with higher export capacity.
The commission’s environmental staff concluded that construction and operation of the project would have limited effects on most resources. It identified long-term effects on wetlands, forests, visual resources and air quality, however, and recommended project-specific mitigation measures. The staff said consultations under Section 106 of the National Historic Preservation Act would be completed before construction begins. It said commissioners would take its environmental recommendations into account when making their decision. The project review thus included conditions and measures to address specific impacts, alongside an overall impact conclusion. Completing the consultations and recommended measures remains part of the process leading up to construction.
Regulatory approval remains separate from the final investment decision, which Cheniere has tied to obtaining all required approvals and permits and securing adequate commercial and financing arrangements. On May 28, 2026, the company signed a contract with Bechtel to design, engineer, procure components for and build Phase 1, and issued a limited notice to proceed with engineering and early procurement work. In October 2026, Sabine Pass signed a long-term agreement with QatarEnergy to supply up to 2 million tons of LNG a year, with deliveries set to begin in the early part of the next decade and continue through 2054. One million tons a year under the agreement, among other conditions, is tied to a positive final investment decision for Phase 1. The Phase 1 loan is also intended to cover about 50% of the project’s estimated total costs, but its closing and funding are contingent on a positive final investment decision. The project’s next step therefore remains completing the commercial, financing and regulatory requirements identified by the company before making the investment decision.