Venture Global Targets CP2 Expansion Decision in 2027, With Capacity of 10 Million Tonnes a Year
Key Facts
Venture Global is targeting an early 2027 final investment decision for the CP2 expansion, with capacity of 10 million tonnes a year, and a decision on the first phase of the Blackmines expansion near midyear, according to the third-quarter earnings call transcript. The two dates put the expansion plans on similar timelines, while referring to different projects and phases. On the call, the company set July 2027 as the target for first production from CP2 and also expected to ship 10 to 20 cargoes in the third quarter of that year. These milestones relate to the first phase of the existing project, while the early 2027 date concerns the final investment decision for the 10 million-tonne-a-year CP2 expansion. For the first phase of the Blackmines expansion, the company is targeting a decision near mid-2027.
The investment plans coincide with progress in preparing CP2. In its third-quarter results statement, the company said 24 of 36 liquefaction units had arrived at the site as of the announcement. It added that a significant amount of gas pre-treatment and power equipment was also on site. The unit count provides an indication of procurement progress for the project, while the first-production target for its initial phase remains July 2027, according to the earnings call. At Blackmines, the company said it had ordered much of the long-lead equipment needed for the expansion. The orders include eight liquefaction trains and gas compression systems for the Cloud Connector line, according to the statement. This reflects the start of securing equipment with long delivery times ahead of the targeted investment decision for the expansion’s first phase near mid-2027.
The current first phase at Blackmines is entering commercial operations, having started commercial operations on October 31, 2026, according to the company statement. The company said in the statement that it had loaded six cargoes for offtake customers as of the announcement. These figures provide operating indicators for the facility after commercial operations began, alongside preparations for its next expansion. The company plans to seek a final investment decision on the first phase of the expansion near mid-2027, according to the earnings call transcript. The company’s timeline therefore combines operations at the current phase with expansion work for which the investment decision is targeted next year.
Financially, Venture Global posted revenue of $4.8 billion in the third quarter of 2026, up 43% from the same quarter in 2025, while net income reached $2.5 billion, up 493% year over year, according to the results statement. The company attributed the increase in net income and adjusted earnings primarily to higher LNG sales volumes, particularly from Blackmines, and higher net sales prices after feed gas costs. On the earnings call, it said it also recorded a non-cash gain of $1.4 billion from interest rate swaps during the quarter. The company raised its 2026 consolidated adjusted EBITDA guidance to a range of $10.0–$10.3 billion, from $8.7–$9.1 billion previously. The updated guidance is based on a weighted average liquefaction fee of between $21 and $22 per million British thermal units for the remaining unsold cargoes, according to the company statement.
The company presented indicators for the European gas market in the context of its plans. On the earnings call, it said monthly LNG imports into Western Europe had risen 45% since July 2026. It added that EU gas inventories were at their lowest level for the start of November since 2013, despite increased imports, and that storage builds were trailing usual levels. These indicators come as the company sets dates for its expansions and targets the start of CP2 production in July 2027 from the first phase of the existing project. For power outside its LNG business, the company announced framework agreements in October 2026 with GE Vernova and Baker Hughes for up to 16 power units, with capacity of 720 megawatts each. The company said the agreements support the expansion of a power network and infrastructure independent of the public grid, as part of a potential business serving data centers.
In the nine months ended September 30, 2026, net income rose by about $3.2 billion, and consolidated adjusted EBITDA increased by about $2.2 billion compared with the same period in 2025, according to the results statement. The company attributed the increase mainly to higher LNG sales volumes, particularly from Blackmines. This comparison provides a longer-term backdrop to the third-quarter results, which came alongside updates on expansion projects and financial guidance. Venture Global shares closed at $12.5 on November 17, 2026, according to EL7 data. This figure does not indicate the stock’s move during the results announcement session; it records the close on that day, before the date of the news.
Looking ahead to 2027, Venture Global maintained its expectation for total shipments of 575–625 cargoes during the year, according to the third-quarter earnings call transcript. It said it would provide further production and pricing guidance for 2027 during its fourth-quarter earnings call early next year. The expected update follows the company’s target dates for investment decisions on the CP2 expansion in early 2027 and the first phase of the Blackmines expansion near midyear. It also set July 2027 as the target for first production from CP2’s first phase, alongside an expectation of 10 to 20 cargoes in the third quarter. These dates combine targeted expansion decisions with operating and shipping indicators the company said it would track during the year.