Lithium Americas Needs an Additional $995 Million for Thacker Pass Project

Key Facts

1The company estimated an additional funding need of about $995 million, including $895 million for capital expenditures.
2The company expects to provide $650 million through its contributions and $315 million from reserve accounts funded by a Department of Energy loan.
3The Phase 1 capital cost estimate was $3.83 billion, compared with $2.93 billion in the December 2024 report.
4The company's shares fell more than 12% in trading on Wednesday, November 11, 2026.

Lithium Americas estimated an additional funding need of about $995 million for the Thacker Pass project in an update issued on November 11, 2026, raising its Phase 1 capital cost estimate to $3.83 billion, including contingency. The additional need comprises $895 million in capital expenditures, $58 million to increase sustaining expenditure reserve requirements through March 2028, and a net $42 million increase in other items, the company said. It expects to meet the amount through joint venture level contributions and funds deposited in reserve accounts under a U.S. Department of Energy loan. The increase highlights execution and financing pressures at the lithium mine under construction in Nevada. The company also said its contributions will increase its ownership stake in the joint venture, while it works with the department and General Motors to finalize the ownership implications.

The company expects to contribute $650 million to the joint venture and use $315 million currently available in reserve accounts funded under the Department of Energy loan as needed. It said the contributions will increase its stake in the project, while it continues to work with the department and General Motors to finalize the ownership implications of the financing arrangements. The company signed amendments to the department's loan documents that will reduce funding requirements for the sustaining expenditure reserve by about $30 million during and after the ramp-up period. This reduction comes against the $58 million increase in reserve requirements included in the additional funding estimate. The company did not specify in the update the new ownership percentage it will hold after the contributions.

The updated Phase 1 capital estimate was $3.83 billion, compared with $2.93 billion in the December 2024 technical report, the company said. It said the combined impact of tariffs and logistics was about $100 million, but its estimate of tariff exposure alone fell to about $60 million after most equipment and materials had been received. By contrast, it estimated the impact of installation rates for piping, steel and equipment at about $245 million, and the impact of inflation in craft labor wages and compensation at about $150 million. The company linked these increases to regional competition for skilled labor. The items show that labor and installation costs represent greater pressure than standalone tariff exposure in the company's estimate.

The company added about $100 million for increased staffing levels at its engineering, procurement and construction contractor and its subcontractors, and about $150 million for their employees' wages. It also included an additional contingency of about $150 million, equal to 10% of estimated costs it has not yet committed to or spent. The company said cost estimate risks had declined as engineering and procurement advanced, and that earthwork and geotechnical work had passed its key milestones. But it identified recruiting and retaining qualified craft workers, along with maintaining planned installation rates, among the main remaining risks. It reported that 4.7 million work hours had been completed at the site without a serious injury or lost-time incident, while 80% of the required fabricated piping materials had arrived or were in transit by the end of October 2026.

Phase 1 construction costs included in the estimate totaled $2.2613 billion cumulatively through September 30, 2026, while total development costs and capitalized interest reached $2.4476 billion. The company said the financial information was preliminary and could change when full results are released. It had about $1.3 billion in cash and restricted cash on the same date, including $359.5 million held by the joint venture. That compares with the estimated additional funding need of about $995 million, which the company said it expects to fund through contributions and available reserves. The figures provide a snapshot of liquidity at the end of September and the funding sources the company cited in its update.

Lithium Americas is targeting mechanical completion of Phase 1 in late 2027, followed by a ramp-up to commercial production during 2028. At full capacity, the company expects to produce 40,000 tonnes a year of battery-grade lithium carbonate. It is also targeting completion of a shipping and transloading facility west of Winnemucca in 2027 to serve as a logistics hub supporting the project. Full third-quarter results are scheduled for release on November 12, 2026, following the quarter close and review. In trading on Wednesday, November 11, the company's shares fell more than 12%, according to The National.