Phase 1 cost at Thacker Pass rises 31% to $3.83 billion

Key Facts

1Lithium Americas raised its estimated cost for Phase 1 to $3.83 billion from $2.93 billion.
2The estimate increased by about 31%.
3The company estimated the additional funding need at about $995 million.
4The company expects to cover the need with $650 million in contributions and $315 million from available reserves.

In an update issued on November 11, Lithium Americas raised its estimated cost for the first phase of the Thacker Pass project in Nevada to $3.83 billion, from a previous estimate of $2.93 billion. Reuters said the increase was 31%, while the company said the updated estimate includes a contingency allowance. The increase comes as construction continues on the project, which the company is developing through a joint venture. The company estimated that the additional funding need resulting from the revised spending estimate and other assumptions is about $995 million. It said this need would be covered by contributions from Lithium Americas and funds available in reserve accounts linked to a U.S. Department of Energy loan.

The additional $995 million need comprises $895 million in higher capital expenditures, $58 million to increase the sustaining-cost reserve account requirements through March 2028, and a net increase of $42 million across other items. The company said it expects to contribute $650 million at the joint-venture level, while drawing on $315 million currently held in reserve accounts as needed. Those accounts are linked to the U.S. Department of Energy loan. Lithium Americas said its contributions would increase its ownership stake in the joint venture. The company would therefore cover most of the expected additional funding through direct project contributions and loan reserves.

The company attributed the higher cost to a range of construction pressures, including an estimated combined impact of tariffs and logistics of about $100 million. It also estimated the impact of craft labor wage inflation and compensation packages at about $150 million. Higher installation rates for piping, steel and equipment contributed about $245 million to the increase, it said. The company also estimated an impact of about $100 million from staffing levels across engineering, procurement and construction management teams and contractors. These items indicate that part of the increase came from the cost of execution, labor, materials and logistics services.

Lithium Americas updated its Phase 1 capital expenditure guidance for fiscal 2026 to a range of $1.7 billion to $2.0 billion, saying spending is expected to peak in that year. The spending is part of a project that also relies on government financing; in a previous filing with the U.S. Securities and Exchange Commission, the company reported receiving a conditional commitment for a $2.26 billion loan from the Department of Energy. The loan was allocated to eligible construction costs for the processing facilities at Thacker Pass. According to the company’s update, the reserve accounts linked to the loan provide $315 million in financing available as needed. Lithium Americas said the expected $650 million in contributions would increase its stake in the joint venture.

On execution, the company said about 1,900 people were on site as of September 30, 2026, including more than 1,600 craft workers. It added that detailed engineering was complete and procurement of equipment and materials was more than 90% complete. The company is targeting mechanical completion of Phase 1 in late 2027. It expects to ramp up commercial production during 2028, while the phase is designed to produce a nameplate 40,000 tons per year of battery-grade lithium carbonate at full capacity. Chief Executive Jonathan Evans described the project as aiming to provide "the largest fully integrated domestic source of battery-grade lithium carbonate in America."

Lithium Americas said its full third-quarter 2026 results would be released on November 12. General Motors shares closed at $88.69 in the November 10 session, according to EL7 data. That price reading remains tied to the session before the company’s November 11 update. Investors are focused on financing the cost increase and on the impact of the contributions on Lithium Americas’ ownership of the joint venture. The company has also set its targeted execution and production dates of late 2027 and 2028 as part of its announced Phase 1 plan.