EL7 Research · Energy and Infrastructure
22 September 2026
On 3 August 2026, Texas Governor Greg Abbott wrote that applications to connect to the state's power grid had reached around 474 gigawatts, with around 90% for data centres. The figure equals 5.20 times the grid's highest recorded demand: 91.1 gigawatts on 22 July 2026. On 21 September, the governor directed the state's environmental protection agency (TCEQ) to halt permits for data-centre projects until audits are completed.
That is the news. What the headlines do not say is that the figure on which the entire decision was based was not published by ERCOT, the grid operator, but appeared in the governor's letter. ERCOT itself does not take the queue at face value: in its presentation to the state Senate Business and Commerce Committee, it cut data centres' contribution to the 2030–2031 peak from around 78 gigawatts before adjustment to around 22 gigawatts after it — meaning only 28.2% survives its pruning.
Then came the paradox. On Friday 18 September, the Public Utility Commission of Texas (PUCT) approved its final large-load interconnection rule, dropping the instrument proposed in its March draft: a non-refundable interconnection fee of 50,000 dollars per megawatt. The draft meant 50 million dollars for a one-gigawatt application; the adopted rule imposes a flat study fee of 100,000 dollars regardless of the application's size — meaning the cost of applying for an additional gigawatt is zero. Three calendar days later, the governor froze permits because the queue was too large to bear.
The question remains: does the demand exist at all? The answer comes not from the queue but from the ledger. NRG disclosed that EBITDA for its Texas segment was 381 million dollars in Q2 2026, down 131 million dollars from the prior year, “primarily driven by lower load and energy prices”. Average around-the-clock power prices in the Houston area were 33 dollars per megawatt-hour during the quarter, 8% below the prior year and far below the company's planning assumption of 52 dollars.
Interconnection applications in gigawatts, versus the grid's actual record peak demand
| Series | Date | Value |
|---|---|---|
| ERCOT grid interconnection applications | 31 December 2024 | 63.00 |
| ERCOT grid interconnection applications | 30 November 2025 | 226.00 |
| ERCOT grid interconnection applications | 30 June 2026 | 438.00 |
| ERCOT grid interconnection applications | 3 August 2026 | 474.00 |