Venture Global Targets Two LNG Expansion Investment Decisions in 2027

Key Facts

1Venture Global is targeting a final investment decision on the CP2 expansion in early 2027, with planned capacity of 10 million tonnes per year.
2The company is targeting an investment decision on the first phase of the Plaquemines expansion around mid-2027, with first production in 2029, subject to regulatory approvals.
3The company has ordered much of the long-lead equipment for the Plaquemines expansion, including eight liquefaction trains.
4Third-quarter 2026 revenue was about $4.8 billion, up 43% year over year.

Venture Global is targeting a final investment decision on the CP2 expansion in early 2027, followed by one for the first phase of the Plaquemines expansion around midyear, according to the company’s third-quarter results. The plans would add new capacity to its LNG portfolio, but the timelines differ between the projects. The company plans a 10 million tonnes per year expansion at CP2, targeting initial production in late 2028, according to its results guidance. For Plaquemines, the expansion decision remains contingent on regulatory approvals, while the company is targeting first LNG production in 2029. Venture Global has thus set investment decision targets in the first half of 2027, with production expected to begin at different times.

Preparatory work at both projects is advancing alongside preparations for the two decisions. The company said it has already ordered a substantial share of the long-lead equipment for the Plaquemines expansion, including eight liquefaction trains and gas compression systems for the Cloud Connector pipeline. This indicates that equipment procurement is under way ahead of the targeted final investment decision, but does not mean that all equipment orders for the gas expansions at both projects have been placed. At CP2, the company said 24 of 36 liquefaction units were on site as of the third-quarter results announcement, along with most of the gas processing and power equipment. This physical progress provides context on the project’s readiness, while the investment and production dates remain the company’s stated guidance.

On its third-quarter earnings call, the company brought forward its target for first LNG production from CP2 to July 2027, about 24 months after the investment decision for the first phase. It said this schedule would be faster than its previous record of 29 months between an investment decision and first production. It is also targeting shipments of between 10 and 20 cargoes from CP2 in the third quarter of 2027. These operating milestones differ from the results guidance for initial production in late 2028 for the 10 million tonnes per year CP2 expansion: the July date refers to first production from the first phase, while the other guidance applies to the planned expansion. Venture Global said its experience at Plaquemines could help it ramp up CP2 production faster.

The first phase of Plaquemines provides the company with an operating precedent for expanding production. Commercial operations began on October 31, 2026, and the company said it had loaded six shipments for customers under sales and purchase agreements as of the third-quarter results announcement. On the earnings call, it said Plaquemines produced 234 cargoes in its first year and said it expects lessons from the facility to accelerate the CP2 production ramp-up. This comes as the company targets an investment decision for the first phase of the Plaquemines expansion around mid-2027, with production set to begin in 2029, subject to regulatory approvals. The timeline brings together operations at the current phase, which has started commercially, and expansion work that has not yet reached a final investment decision.

Alongside its LNG expansion, Venture Global presented off-grid power and infrastructure for data centers as a potential additional business. The chief executive said the company is expanding its established capabilities in building and operating power and infrastructure networks that function independently of the grid. In October 2026, the company announced framework agreements with GE Vernova and Baker Hughes for energy services, covering up to 16 new power units, each with capacity of 720 megawatts. The company places this initiative within its effort to meet data center needs, alongside its core LNG business. The move adds another dimension to its infrastructure investment plans without changing the announced decision timelines for the CP2 and Plaquemines expansions.

Third-quarter results showed revenue and profit growth in the period when the company announced its expansion plans. Revenue was $4.8 billion, up 43% from the third quarter of 2025, while net income reached $2.5 billion, up 493% year over year. The company also raised its 2026 adjusted EBITDA guidance range to $10.0–10.3 billion from a previous range of $8.7–9.1 billion. These figures were reported for the same period as the CP2 and Plaquemines updates, alongside the additional focus on data center infrastructure. VG shares closed at $12.5 on November 17, 2026.

Against the backdrop of gas demand, the company said monthly LNG imports to Western Europe have risen 45% since July 2026. It added that EU gas inventories were at the start of November at their lowest comparable level since 2013. Venture Global cited these indicators in the market context for its projects as it prepares for the two expansion investment decisions. Looking ahead, the company said it will provide further guidance on 2027 production and prices during its fourth-quarter earnings call early next year. It maintained its total shipment outlook at 575–625 cargoes in 2027.