Infra and HUMAIN Sign Financing of Up to SAR 2.5 Billion for AI Data Centers

Key Facts

1The Infra and HUMAIN agreements are worth up to SAR 2.5 billion, or about $667 million, and were announced on November 9, 2026, after being signed in Riyadh on November 8.
2The GPU purchase facility is worth up to SAR 1.1 billion and is tied to an IT load of about 25 megawatts.
3The power infrastructure facility is worth up to SAR 1.4 billion, and the infrastructure is designed to support future IT capacity of up to 1 gigawatt.
4HUMAIN plans to deploy 3 gigawatts of AI data center capacity by 2030.

Saudi Arabia’s National Infrastructure Fund (Infra) and HUMAIN have signed two agreements worth up to SAR 2.5 billion, or about $667 million, to support computing and power infrastructure in the Kingdom. The fund announced the deal on November 9, 2026, after it was signed in Riyadh on November 8. The agreements are the first announced deals under Infra’s program to finance AI data centers. The financing is split between a facility to purchase and deploy GPUs and another for substations, power transmission and connecting HUMAIN data centers to the grid. The agreements set a ceiling for the financing, while their terms focus on equipping the computing and power infrastructure needed to expand capacity.

The first facility is capped at SAR 1.1 billion, or $293.3 million, and is allocated to purchasing and deploying GPUs. Deployment and operation of the units are tied to an IT load of about 25 megawatts. This makes computing equipment a direct use of the financing, alongside the infrastructure needed to operate data centers. HUMAIN CEO Tareq Amin said the facilities “will help accelerate the deployment of advanced computing capabilities.” He added that the required infrastructure includes the power needed for those capabilities. This stated use places the financing toward building computing capacity, rather than providing general support for digital transformation.

The second facility is worth up to SAR 1.4 billion and covers substations, power transmission and connecting HUMAIN data centers to the grid. The power infrastructure is designed to support future expansion to up to 1 gigawatt of IT capacity. This component complements the GPU financing by linking computing infrastructure with power and grid connection requirements. The allocation of the SAR 2.5 billion ceiling reflects separate funding for GPUs and power facilities. Amin said the agreements would accelerate deployment of the infrastructure needed for advanced capabilities. The infrastructure’s design to accommodate future expansion provides room to increase data center capacity as the project grows.

The agreements follow a strategic financing framework announced by Infra and HUMAIN in Davos on January 21, 2026, worth up to $1.2 billion. The fund described the framework as non-binding, and it was aimed at AI and digital infrastructure projects in Saudi Arabia. The framework targeted the development of up to 250 megawatts of hyperscale AI data center capacity. It also included exploring an investment platform for data centers with the participation of local and global institutional investors. The November agreements differ from the January framework in the nature of the announcement: the former are announced deals under the financing program, while the latter was a framework with non-binding terms. The November announcement specifies uses for computing and power, in the context of an earlier framework covering data center capacity and a potential investment platform.

Infra CEO Ismail Al-Salloum said the fund aims to “unlock investments beyond Infra’s own commitment.” He said the fund’s role includes advancing project readiness and bankability, while directing capital according to commercial viability and economic value. This description places the HUMAIN agreements within the program’s broader aim of preparing infrastructure projects to attract investment beyond the fund’s contribution. The AI data center financing program aims to support the AI ecosystem and accelerate national digital capacity targets. The program also cites strengthening the Kingdom’s position as a regional AI hub in line with Vision 2030. The fund presents this aim as part of the program’s objectives, alongside the financing details allocated to the computing and power projects.

HUMAIN plans to deploy 3 gigawatts of AI data center capacity by 2030 to meet regional and global demand for computing. This long-term target puts the November agreements in the context of an expansion that exceeds the future IT capacity of 1 gigawatt the power infrastructure is designed to support. The financing announcement covers GPUs, substations, power transmission and grid connections, while the company’s target is to deploy total capacity of 3 gigawatts. The announcement does not specify a timeline between the agreements’ infrastructure and the 2030 target. The announced step remains initial financing under Infra’s program, while HUMAIN’s plan sets out its targeted expansion through the end of the decade.