Hyperscale Data Needs $74.8 Million to Complete 20-Megawatt Michigan Deployment
Key Facts
Hyperscale Data estimated the remaining costs to complete deployment of 20 megawatts at its Michigan facility at about $74.8 million, according to its quarterly filing with the U.S. Securities and Exchange Commission. The cost is part of a project to build, equip and operate the contracted capacity, with total estimated costs of $122.1 million. The company had paid about $47.3 million as of October 31, 2026, and expects to pay the remainder between November 2026 and March 2027. It said cash and available liquidity sources are not expected to be sufficient to meet obligations and capital expenditures during the twelve months following the issuance of the financial statements. It added that this raises substantial doubt about its ability to continue as a going concern.
The figures at the end of September show the extent of the liquidity pressure: cash and cash equivalents totaled $17.3 million, alongside $27.8 million in restricted cash. Current liabilities totaled about $231.2 million, exceeding current assets by about $128.1 million. After month-end, the company received $15 million in total from two closings of convertible-note financing. The first closing provided $10 million on November 6, followed by $5 million from the second closing on November 18. Even so, the company said available liquidity is insufficient for its expected needs and that it cannot be certain its financing plans will be implemented effectively and sufficiently to alleviate the going-concern uncertainty.
The company’s financing sources included the sale of about 211.6 bitcoin on November 6, for gross proceeds of about $16 million. It said it used part of the proceeds to repay Japanese government bonds in full, including $12.8 million in principal and an early repayment premium of about $1.3 million. The company also issued convertible notes for gross proceeds of $10 million on November 6, then completed a second closing for proceeds of $5 million on November 18. The parties may agree to an additional issuance for gross proceeds of $10 million during the three months following the second closing, subject to shareholder approval. The company cannot guarantee that additional capital will be available when needed or on acceptable terms.
The deal behind the spending dates to June 23, 2026, when the company entered into an agreement to provide data-center services for about 20 megawatts of AI computing at its campus in Dowagiac, Michigan. The contract is valued at about $1.2 billion if the customer exercises its two five-year extension options, a hypothetical total contract value rather than the cost of building the facility. The value could rise to about $3 billion if the customer exercises its right of first offer to add 32 megawatts during the first two years of the agreement. The company is targeting readiness of the first phase, with 10 megawatts of capacity, in December 2026, followed by completion of another 10 megawatts by the end of March 2027. It said one-time customer payments and partial advance payments of occupancy fees will offset some of the financing needs.
The spending comes as the company shifts its Michigan facility away from bitcoin mining, having halted mining there as of September 1, 2026, ahead of converting the site into an AI data center. Cryptocurrency-mining revenue fell 65% in the third quarter to about $2 million, from $5.7 million in the same period a year earlier. In contrast, the company’s total third-quarter revenue rose to $44.848 million, from $24.328 million in the third quarter of 2025. But net loss attributable to common shareholders was $17.954 million, compared with $15.256 million a year earlier. Before the end of September, the company sold about 110.3 million shares through an at-the-market offering program, generating gross proceeds of about $47.9 million.
Plans to complete the facility carry risks tied to the timing of spending and the availability of financing. The company said actual costs and their timing could change depending on construction progress, equipment purchases, installation costs, customer deployment schedules and financing availability. It also said additional liquidity may not be available when needed or on acceptable terms. The convertible notes carry annual interest of 8%, rising to 18% in the event of default, with an initial maturity date of February 5, 2027, which may be extended to May 5, 2027, if shareholder approval and compliance conditions are met. On November 17, the company announced that it expects to begin a stock exchange offer around November 20 to purchase up to 192,308,000 shares in exchange for units comprising cash and preferred stock, subject to approvals and closing conditions. The company’s shares, which trade under the ticker GPUS, closed at $0.157 on November 18, 2026.