Data Center Investment Reached $565 Billion in 2025, With Spending of $4 Trillion Expected by 2030

Key Facts

1Data center investment reached $565 billion in 2025, with a further $4 trillion in related spending expected by 2030.
2The agency expects data center electricity consumption to reach 1,000 terawatt-hours by 2030 under its stated policies scenario.
3Potential observed capacity for AI data centers rose tenfold over 24 months to 17 gigawatts.
4About 180 gigawatts of gas-fired generation capacity had been planned for data centers in the United States through August 2026.

The International Energy Agency estimated that data center investment reached $565 billion in 2025 and forecast a further $4 trillion in related spending by 2030, driven by the AI boom. The estimate puts spending on infrastructure tied to the sector at the heart of the current technology expansion, as companies race to build new computing capacity. In a separate forecast for electricity consumption, the agency sees usage rising from 485 terawatt-hours in 2025 to 950 terawatt-hours in 2030, or about 3% of global electricity demand that year. The difference between the figures reflects that capital investment and energy consumption are separate measures of data center expansion. Movements in IREN, Applied Digital and TeraWulf shares in the November 19, 2026 session could not be verified from a reliable open source.

Electricity demand is accelerating alongside investment growth: global data center consumption rose 17% in 2025, while consumption at AI-focused facilities increased 50%, according to the agency. The gap shows that facilities serving AI workloads were a faster driver of the increase during the year. Under its stated policies scenario, the agency expects sector consumption to double to 1,000 terawatt-hours by 2030. It says AI-optimized data centers will drive about three-quarters of consumption growth in this scenario. The long-term spending estimate is therefore tied to an expected expansion in electricity use, not simply an increase in the number of facilities.

Indicators for AI-dedicated infrastructure point to rapid expansion in projects under construction or in the planning stage. Potential capacity tracked by the agency using satellites rose tenfold over 24 months, reaching 17 gigawatts in 2026. The agency tracks 93 AI data centers and estimated that their combined capacity could reach about 50 gigawatts once completed. Those estimates are tied to the completion of the sites, while the 17-gigawatt figure represents potential capacity currently observed. Connecting these projects to grids and securing chips and power equipment means that expansion plans depend on the availability of inputs beyond financing alone.

But infrastructure expansion faces supply and connection constraints. The agency said queues to connect data centers to grids stretch for years in some areas, and bottlenecks include advanced chip packaging, computer memory and power equipment. It expects these bottlenecks to persist in the coming years. It also said shortages of high-bandwidth memory are likely to continue until at least the end of 2027, alongside intensifying constraints on power supplies and advanced chip manufacturing. These constraints pose practical challenges for the timing of projects coming online, even as investment forecasts remain high.

U.S. gas-fired power projects illustrate the gap between planning and operation. About 180 gigawatts of gas-fired capacity had been planned to serve data centers through August 2026, according to the agency. But a backlog of orders for gas turbines means most of this capacity is not expected to come online before the 2030s. On the financing side, capital spending by five major technology companies exceeded $400 billion in 2025, and the agency expects a further increase of 75% in 2026. This combines substantial capital flows with a longer timeline for providing some of the energy sources needed to operate the facilities.

In equities, Applied Digital closed at $14.45 and TeraWulf at $12 on November 18, 2026, according to EL7 data. These two prices provide context for the previous session, without establishing the direction of either stock in the November 19 session. The gains attributed to the two companies in that session could not be verified, and IREN’s share movement or price could not be confirmed. The agency’s estimates for investment and electricity consumption remain sector indicators and do not, on their own, establish that movements in any particular stock were a response to them. Grid, chip and power equipment constraints are expected to continue affecting the timing of expansion, while the agency expects some supply bottlenecks to persist in the coming years.