Paradox Data Secures Option on 89.56 Acres to Expand Arkansas AI Campus

Key Facts

1The exclusive option covers about 89.56 acres in Union County, Arkansas.
2The option term is five years from November 11, 2026.
3The company targets developing capacity of up to about 150 megawatts over the long term.
4Paradox Data paid a $37,500 consent fee and the first annual option fee of $10,000.
5ZSQR shares closed at $1.94 on November 17, 2026.

Paradox Data, a wholly owned subsidiary of Z Squared, secured an exclusive option to purchase about 89.56 remaining acres of a parcel in Union County, Arkansas, under an Assignment and Amendment Agreement dated November 11, 2026. The agreement gives the company five years to exercise the option, whereas the previous option had no specified term, according to a filing with the U.S. Securities and Exchange Commission. The company plans to begin with an initial parcel of up to 10 acres after completing surveys and site investigations. The letter of intent sets the price for that parcel at $20,000 per acre confirmed by the survey. The move is part of a broader plan to develop an AI campus in the county, targeting capacity of about 150 megawatts over time.

When the assignment took effect, Paradox Data paid a one-time consent fee of $37,500, along with the first annual option fee of $10,000, according to the company's filing. The agreement sets the purchase price for the remaining land covered by the option at $33,333.33 per surveyed acre, excluding the initial parcel, which is subject to the separate price in the letter of intent. The option fees and consent fee are not credited against the land purchase price. The $10,000 letter-of-intent deposit, however, will be credited toward the initial parcel's price when the purchase is completed. These terms give the company the right to secure additional land over an extended period, while moving from an option to land ownership remains contingent on exercising the right and completing the purchases.

Before exercising the option, the agreement allows surveying and environmental and engineering assessments. But it requires the seller's prior written consent for intrusive testing, including soil borings or groundwater sampling. This means technical due diligence at the site is subject to specific contractual restrictions, alongside the need to determine the initial parcel's size through surveying. The company said it intends to exercise the option for that parcel after completing the survey and site investigations. The filing did not specify a timetable for completing that work or purchasing the remaining land.

The target of about 150 megawatts remains a development goal, not a description of capacity currently available or under contract. The company said reaching it will require additional power arrangements, customer commitments, financing, permits and construction. In September, it reported that the site was served by an interruptible electricity arrangement with Entergy Arkansas, capped at 8,000 kilovolt-amperes, or about 8.0 megawatts. The service agreement was with the seller, and transferring it to Paradox Data requires Entergy's approval, which the company said it had not obtained at the time of the filing. This highlights the gap between the power supply reported at the time and the ultimate target, while making electricity arrangements one of the conditions for expansion.

The company tied part of the potential consideration for the acquisition to development milestones at the Union County campus. This includes up to $20.0 million in additional preferred shares, which would vest only upon completion of four specified milestones. The first concerns the initial deployment of AI computing capacity at the existing site, while the other three are tied to reaching total capacities of 50, 100 and 150 megawatts. This mechanism makes expansion milestones contingent on completion, rather than treating the targeted capacity as achieved when the land option is announced. The facility at the site had been used for Bitcoin mining, according to the acquisition filing, while the temporary lease for the building and existing parcel expires no later than the second anniversary of its commencement.

The company warned in its filing that it would need to raise substantial additional capital to fund its AI strategy and high-density computing infrastructure. It also noted that it may not exercise the option or complete any land purchase under it, leaving the proposed expansion dependent on financing availability and satisfaction of conditions tied to the site. ZSQR shares closed at $1.94 in the November 17, 2026 session, according to EL7 data. The company said it expects to file its quarterly report for the period ended September 30 no later than November 23, 2026, after requesting an extension to the filing deadline. The expected report date follows the announcement of the land-option terms, while the company continues to describe its capacity target as a phased development plan.