Nvidia Sets Credit Guarantees of Up to $105 Billion for Ohio Data Center Project
Key Facts
Nvidia disclosed credit guarantees capped at $105 billion to support construction of land, power and building structures at the PORTS-Pike campus in Ohio, in an arrangement tied to infrastructure dedicated to OpenAI. The company said in its third-quarter filing that the guarantees cover about 4.25 gigawatts across 9 buildings at the campus owned by SB Energy. The cap does not mean that amount will be paid immediately; the guarantees take effect in stages, with each applying only after the relevant building is complete and ready for service. Nvidia had said in an earlier filing that the first activation was expected in fiscal 2029. The arrangement places the company under a long-term credit obligation tied to the expansion of computing infrastructure, while activation remains subject to the conditions of each phase.
The project is in Pike County, Ohio, and the campus will host Nvidia infrastructure exclusively under 20-year leases to OpenAI, according to the company's filing. The initial guarantees cover capacity of about 4.25 gigawatts, while the planned capacity of the full campus is 8.0 gigawatts-IT, according to an SB Energy filing. Capacity of 3.78 gigawatts-IT remains outside the initial guarantee and is covered only by the possibility of optional credit support at Nvidia's sole discretion. The company previously said it had the option to provide this additional support in stages as the site expands. That means the announced guarantee cap is tied to the initial phase, while the scope of support could expand if the company chooses to activate the remaining option.
The guarantee mechanism is determined when the relevant lease begins, and Nvidia may pay the shortfall between the guaranteed minimum lease value and what the site owner recovers if OpenAI defaults, whether through a replacement lease or a sale of the site. The company said its exposure under the guarantee declines as OpenAI makes lease payments. In an explanation reported by Reuters, the guarantee does not cover the full cost of the project or all of OpenAI's obligations, but covers part of the lease and power payments, along with a commitment to maintain a minimum site value. These terms link the amount of exposure to what can be recovered from the site, rather than turning the announced cap into a direct payment. The project's financing structure remained undetermined at the time of a Reuters report in August 2026.
Nvidia also presents the project as a commercial opportunity spanning successive generations of infrastructure. It said each generation deployed at PORTS-Pike could represent about 1.5 million graphics processing units and roughly $150 billion to $200 billion in revenue for the company. It added that the site could accommodate multiple infrastructure upgrade cycles over 20 years. In an earlier announcement tied to the deal, Reuters reported that Nvidia would invest $1.5 billion in SB Energy. These details combine a conditional credit guarantee with a potential expansion in computing sales over the life of the project.
The guarantee disclosures come as Nvidia reports strong sales growth, particularly in its data center business. The company said revenue in the third quarter of fiscal 2027, ended Oct. 25, was $115.8 billion, up 20% from the previous quarter and 103% from a year earlier. Data center revenue was $107.6 billion, up 110% year over year. Cloud service agreements and data center lease obligations combined rose to $102 billion, compared with $74 billion in the previous quarter. Chief Financial Officer and interim Chief Executive Colette Kress told investors and analysts: "Our momentum is real. Demand is accelerating, and our supply is growing."
The stock's reaction was volatile in the Nov. 18 session, according to the Associated Press. Shares initially rose 2.7% after the company reported results that exceeded analysts' expectations, before erasing their gains and falling to a loss of 2.4%. In its outlook for the following period, Nvidia estimated fourth-quarter fiscal 2027 revenue of $130.0 billion, plus or minus 3%. The company said that estimate assumes no data center computing revenue from China. It also announced a quarterly cash dividend of $0.25 per share on Dec. 23, 2026, for shareholders of record on Dec. 2.
On project execution, the first 800 megawatts of capacity was expected to enter service in 2028, Reuters reported on Aug. 17, 2026. That is consistent with the phased activation mechanism under which Nvidia linked each guarantee's effectiveness to completion of the associated building and its readiness for service. As construction advances and leases begin, the phases in which the company's obligations may arise under the announced cap will become clearer. Support for the additional 3.78 gigawatts-IT remains a discretionary option separate from the initial guarantees. The buildings' timeline and the level of site-value recovery in any default will determine Nvidia's actual exposure.