Bladex Joins $900 Million Financing for 472-Kilometer Argentine Gas Pipeline

Key Facts

1The syndicated financing for the San Matías pipeline project totaled $900 million when it closed in August 2026, with Bladex among the participants.
2The pipeline is 472 kilometers long and links Vaca Muerta to the Gulf of San Matías.
3The project is estimated to cost about $1.3 billion, with the loan covering about 70% of that amount.
4The loan has a 7-year term, with a 3-year grace period.
5The pipeline is designed to transport 27 million cubic meters a day, with construction targeted for completion by mid-2028.

Bladex joined a group of banks that closed a $900 million syndicated financing in August 2026 for Argentina’s San Matías pipeline project, according to law firm Milbank. The financing is earmarked for a project to transport gas from the Vaca Muerta region to the Gulf of San Matías, on the coast of Río Negro province. The loan represents most of the project’s cost, covering about 70% of a total investment estimated at about $1.3 billion, according to LA NACION. Bladex’s participation places it in a deal to finance infrastructure aimed at moving domestically produced gas toward the country’s coast. The project is part of a broader Argentine effort to increase the capacity to bring gas out of Vaca Muerta and develop liquefied natural gas exports.

Santander, Citi, JPMorgan and Itaú led the financing arrangement, while the group of participating banks also included BBVA, Barclays, ICBC and Bank of China, along with Bladex, according to Milbank. The planned pipeline is 472 kilometers long and links the Vaca Muerta shale formation to the Gulf of San Matías, the firm said in its description of the project. The route serves as a transportation link between the production region and a coastal site in a project dedicated to natural gas. Construction costs are estimated at $1.3 billion, while the syndicated loan provides $900 million, or about 70% of the investment. That means bank financing covers most of the project’s estimated cost, with part of the cost remaining outside the announced loan.

The loan has a seven-year term, with a three-year grace period, according to details reported by LA NACION. The newspaper said the financing is based on the project’s future cash flows, secured by long-term transportation contracts. This structure sets the repayment term and grace period, and ties the project’s ability to service its debt to future transportation revenue supported by those contracts. San Matías Pipeline is owned by five energy companies: Pan American Energy, with a 30% stake; YPF, with 25%; Pampa Energía, with 20%; Harbour Energy, with 15%; and Golar LNG, with 10%. The project thus brings together syndicated bank financing and energy company shareholders, while the pipeline serves as an asset for transporting gas from the production region to the coast.

Argentina’s Economy Ministry approved the project in June 2026 under the incentive regime for large investments, classifying it as a pipeline dedicated to natural gas exports. The approval decision set an approximate length of 480 kilometers and transportation capacity of 27 million cubic meters a day. The approximate length in the approval decision differs from the 472 kilometers Milbank cited in its project description, while the design capacity matches the figure Reuters reported via Kitco. Argentina’s Energy Ministry said a joint study with Brazil concluded that Argentina’s resources are sufficient to meet domestic demand and sustain long-term exports. But it said additional transportation infrastructure would be needed to bring larger volumes out of Vaca Muerta, a need directly related to the new pipeline’s function.

The plan targets completion of the pipeline by mid-2028, Reuters reported via Kitco, with capacity of 27 million cubic meters of gas a day once operational. The timeline is also linked to floating liquefaction projects: the Hilli Episeyo vessel is expected to begin operations in 2027, followed by the Esperanza vessel in 2028. Together, the two vessels are planned to produce 6 million tons of liquefied natural gas a year. This places the target completion of the San Matías pipeline before the end of 2028 alongside the planned start dates for the liquefaction facilities, while the pipeline will transport the gas volumes needed to reach the coast. The Energy Ministry says gas export options to Brazil also require new infrastructure development within Argentina, including work to bring larger volumes out of Vaca Muerta.