$24 Billion Investment: Texas Grants SpaceX Environmental Approval for 31.14-Megawatt Gas Plant

Key Facts

1The Texas Commission on Environmental Quality listed a final action on November 16, 2026, concerning the registration of SpaceX’s Starbase facility.
2The plan registers 3 natural gas turbines with total capacity of 31.14 megawatts for on-site use.
3The estimated capital investment for the initial phases is $24 billion.
4The Starbase Commission is scheduled to consider the tax abatement request and economic development agreement on December 9, 2026.

The Texas Commission on Environmental Quality listed a final action on the registration of SpaceX’s production facility in Starbase at 4:18 p.m. on November 16, 2026. The registration describes a natural gas-fired power generation facility with 3 turbines and total capacity of 31.14 megawatts for on-site use. The approval marks a regulatory step in an energy and supercomputing project whose initial phases carry an estimated capital investment of about $24 billion, according to Reuters, citing a project notice. Reuters says SpaceX will build, own and operate the facilities. The environmental decision brings a regulatory aspect of the project to the fore, while some local and tax matters remain under consideration.

The proposed generation consists of 3 simple-cycle natural gas turbines, each with capacity of 10.38 megawatts, according to the commission’s registration. The registered total capacity is 31.14 megawatts and is intended for use on-site. Reuters estimated capital investment at about $24 billion for the initial phases, with the possibility of future expansions. The notice did not specify the size or duration of the property tax abatement sought by the company. The Starbase City Commission is scheduled to consider the request, along with a related economic development agreement, at a public meeting on December 9, 2026.

The plan is also tied to local arrangements concerning land and infrastructure. The Texas Tribune reported that the project site spans 444.45 acres. In an agreement related to removing the site from Brownsville’s jurisdiction, SpaceX offered to fund water and wastewater projects in the city worth $220 million. A temporary 90-day moratorium on data center applications within the city and its extraterritorial jurisdiction took effect in November 2026, according to the newspaper. These matters reflect that the environmental approval comes amid a broader local debate over land use, municipal services and computing projects.

The project has drawn objections related to environmental impacts and services, alongside support from residents focused on job opportunities. The South Texas Environmental Justice Network announced a protest, saying the new facilities could pollute the air, consume water and raise residents’ energy bills. By contrast, Brownsville resident Jannie Melendez said, "There are many people in our community who need jobs, and SpaceX has helped provide them." These views highlight local divisions over potential economic gains and residents’ concerns about the project’s impact. The statements cited did not provide a quantitative estimate of jobs or the expected effects on bills and water.

For the Texas power grid, Reuters said building a dedicated plant could allow the company to avoid waiting years for a connection to the main grid. The project comes as regulators review large interconnection requests from data centers. In a preliminary review dated November 5, the Electric Reliability Council of Texas said 433 of 465 data center loads had submitted an impact questionnaire, covering about 177 gigawatts, or roughly 97% of the capacity requested for interconnection. The council said all 245 large loads, which it defined as 75 megawatts or more, had responded. The 33 projects seeking interconnection of more than 1 gigawatt also represented 36% of the capacity of large loads.

The project is under consideration amid increased political scrutiny of data centers’ effects on electricity and water. On September 21, 2026, Texas Governor Greg Abbott directed the Commission on Environmental Quality to pause data center permits until the Electric Reliability Council completed its review, saying projects must protect the grid and water and complete state audits. Information the council requested from developers includes facilities’ reliance on the grid, on-site generation, water use and tax incentives. The council aims to publish its final analysis of data centers’ effects on states and communities by December 10, 2026; its information request covers facilities of 25 megawatts or more seeking a grid connection. In the market, EL7 data showed SPCX shares closing at $141.7 on November 17, the latest close in the data provided.