TensorWave to Supply OpenAI With 457 Megawatts of AMD Compute Capacity

Key Facts

1The agreed IT capacity to be provided to OpenAI totals 457 megawatts.
2The broader AMD-OpenAI partnership targets deployment of processors with a total capacity of 6 gigawatts.
3Capacity under the TensorWave agreement is scheduled to become available in the first half of 2027, with full deployment expected in early 2028.

TensorWave announced an agreement on November 16, 2026, to provide OpenAI with 457 megawatts of IT capacity, expanding the practical implementation of OpenAI's partnership with AMD. The capacity will run on AMD Instinct MI455X processors across multiple data center sites in the United States, The Next Web reported. OpenAI's head of compute, Oday Roderago, said the agreement advances the partnership the company previously announced with AMD. "We are pleased to advance our previously announced partnership with AMD through this agreement with TensorWave," he said. The resulting infrastructure is dedicated exclusively to serving OpenAI, according to the report.

The sites will use AMD Helios rack-scale systems, with racks connected via Ethernet, according to The Next Web. Dedicating the capacity to OpenAI means the agreement includes no other tenants within that capacity. The data center sites span the United States, but TensorWave and OpenAI have not specified their locations. The companies also did not disclose the contract's value. The announcement therefore sets out the scale and components of the technical capacity, while financial and geographic details remain undisclosed.

The TensorWave agreement falls within a broader AMD-OpenAI framework announced on October 6, 2025, targeting deployment of AMD processors with a total capacity of 6 gigawatts under a multi-year, multi-generation agreement. The broader partnership set out plans to begin deploying the first gigawatt of AMD Instinct MI450 processors in the second half of 2026. Sam Altman said at the announcement that the collaboration marked a step toward building the computing capacity needed to realize AI's potential. AMD Chief Executive Lisa Su also said the partnership brings together the companies' expertise to deliver AI computing at scale. AMD said the collaboration began with MI300X and continued with the MI350X series before moving to MI450 and subsequent generations.

On the financial side of the broader partnership, AMD's chief financial officer said at the time of its announcement that the agreement was expected to generate tens of billions of dollars in revenue for the company. TensorWave's announcement does not specify the value of its separate agreement with OpenAI, so those projections remain tied to the broader AMD-OpenAI partnership. The first capacity under the TensorWave agreement is scheduled to become available in the first half of 2027. TensorWave expects full deployment of the contracted capacity to be completed in early 2028. The timetable sets out a phased rollout, beginning with initial availability and ending with full deployment across the U.S. sites.

Open on chart