SEC Investigates T1 Energy Disclosures on 45X Credits and $34.7 Million Quarterly Loss

Key Facts

1The SEC notified T1 in September 2026 of an investigation covering disclosures about 45X credit eligibility and accounting matters.
2The company had generated $155.3 million in 45X credits through the third quarter of 2026.
3The loss from continuing operations was $34.7 million in the third quarter of 2026, compared with $130.8 million a year earlier.
4T1 shares closed at $1.91 on November 13, compared with $1.97 on November 12.

T1 Energy said the U.S. Securities and Exchange Commission’s Fort Worth regional office notified it in September 2026 that it had opened an investigation into the company’s public disclosures about its eligibility for production tax credits under Section 45X, as well as certain accounting matters. The company disclosed the investigation in its quarterly filing with the SEC, published on November 12. The investigation comes as T1 said it had generated $155.3 million in 45X credits through the end of the third quarter and was in advanced talks to monetize them. “The Company intends to fully cooperate with the SEC investigation,” the company said in the filing. It added: “The duration or outcome of the investigation cannot be predicted at this time.”

The regulatory matter links one of the issues disclosed in the company’s quarterly filings to an important source of funding for its manufacturing operations: T1 said in its third-quarter results that talks to monetize the credits had reached advanced stages. The company did not disclose an outcome or expected end date for the investigation, nor did it estimate its financial impact. In a separate statement cited by Bloomberg, the agency said T1 shares fell 7.5% in after-hours trading following the disclosure, and that the company declined to comment beyond what was in its filing. In the November 13 session, the stock closed at $1.91, compared with $1.97 on November 12. That daily change alone does not establish that the investigation caused the stock’s move in the following session.

On the operations front, T1 produced 1,056 megawatts of modules at its G1_Dallas facility in the third quarter and built inventory of 326 megawatts to meet 2027 deliveries. The company said quarterly production was the second-highest rate in its history. Its loss from continuing operations was $34.7 million, or $0.12 per share, compared with a loss of $130.8 million in the third quarter of 2025. Gross margin was 8.5%, while adjusted EBITDA was a deficit of $16.4 million. The quarterly results thus combined expanded production and inventory with continued losses, while the investigation remains focused on credit disclosures and certain accounting matters.

T1 said it expects annual production at G1_Dallas of between 4.0 and 4.2 gigawatts in 2026, at the upper end of its previous range of 3.1 to 4.2 gigawatts. It also issued preliminary guidance for production of 5.3 gigawatts in 2027. The company said it had signed new agreements to supply more than 1.58 gigawatts of solar modules, and that more than 3.5 gigawatts of its 2027 manufacturing capacity was contracted for deliveries scheduled during that year. As of September 30, cash, cash equivalents and restricted cash totaled $137.0 million, including $59.5 million in unrestricted cash. These operating and financial indicators provide context for the investigation’s importance to the company, while T1 said its duration and outcome remain unpredictable.

The quarterly report also covers matters separate from the new investigation into 45X disclosures and accounting. T1 said it received, in November 2025, grand jury subpoenas from the Department of Justice, along with an executive and a board member, seeking documents concerning sales of company shares in the second half of 2023. It also received a voluntary request from the SEC for similar information. The company said it believes the trades involved shares pledged as collateral for a personal loan and were approved under its insider trading policy, and that it is cooperating with the Department of Justice and the SEC on that matter. It also noted a separate patent dispute brought by First Solar and said it disputes the allegations. The U.S. International Trade Commission hearing related to the dispute is scheduled to begin on February 16, 2027.

Regarding its G2_Austin project, the company said completing a comprehensive financing solution remains its top priority. It warned, however, that there is no assurance it will agree on definitive documents or complete the financing in a timely manner and on acceptable terms, or complete it at all. The company therefore lists financing among the matters still awaiting resolution, alongside plans to increase production and fulfill contracted deliveries in 2027. As for the SEC investigation, T1 said it would cooperate, without specifying an expected duration or outcome. The filing does not disclose a publicly announced next date for the investigation.