Key Facts
Saudi Aramco aims to raise gas sales from the Jafurah field to 2 billion standard cubic feet a day by 2030, after production began in December 2025, as part of a broader expansion of the company's gas supply. The company said the target is part of its ambition to gradually expand production, with its plan underpinned by large gas and condensate reserves. Jafurah's development is part of Aramco's efforts to strengthen gas supplies to the domestic market and expand output of associated liquids. The company describes the field as the largest unconventional gas field discovered in Saudi Arabia and the Middle East's largest liquids-rich shale gas reservoir. A claim that a new sixth phase was launched or that a package to build two compression plants was offered on November 16 could not be verified through a reliable open source, so it is not a confirmed development in this report.
Aramco estimated Jafurah's resources at about 229 trillion standard cubic feet of gas in place and 75 billion standard barrels of condensate in place. The company said estimates for gas and condensate had been raised to these levels, placing the project among its largest unconventional assets. Aramco is counting on developing these resources to produce gas and associated liquids, targeting multiple outputs beyond gas sales. By 2030, Aramco expects to produce 420 million standard cubic feet a day of ethane. It also targets about 630,000 barrels a day of natural gas liquids and condensate over the same period.
Jafurah's target is part of Aramco's broader plan to increase sales gas production capacity by about 80% by 2030 compared with 2021 levels. The company announced the target in February 2026, saying gas growth would support a more efficient mix for domestic power generation. It added that the expansion would strengthen the Kingdom's liquid-fuel displacement program. Aramco thus links increased gas supplies to their use in the power sector and to making more liquid fuels available for other uses. The overall target includes projects beyond Jafurah, so the company does not attribute the entire growth rate to the field alone.
Estimates of total investment over Jafurah's life cycle date to an Aramco announcement in 2021, when it said expected total spending would exceed $100 billion. The figure is an estimate for the project's life cycle as reported at the time, not a disclosed value for a work package or a specific phase in November 2026. In the context of the broader gas expansion, the company said in February 2026 that investments could generate an additional $12 billion to $15 billion in operating cash flow in 2030. Aramco linked this estimate to future demand levels for sales gas and liquids prices. The estimate therefore remains conditional on these variables and does not represent a guaranteed return or a realized outcome.
On the project timeline, development of Jafurah's second phase is targeted for completion in 2027, according to Aramco's third-quarter 2026 interim report. The phase includes a major expansion of the Jafurah Gas Plant and construction of the Riyas natural gas liquids fractionation plant. This precedes the company's longer-term target of raising gas sales from the field to 2 billion standard cubic feet a day by 2030. Aramco also places Jafurah at the heart of its gas expansion program; Chief Executive Amin Nasser said the field is "a cornerstone of our ambitious gas expansion program." He added that supplies would support the petrochemicals industry and energy demand from growth sectors, including artificial intelligence data centers in the Kingdom.