$588 Million Financing Closes for 900-Megawatt Egyptian Wind Farm

Key Facts

1The joint financing closed at about $588 million, and the JBIC loan reaches about $285 million.
2The wind farm near Ras Ghareb has a capacity of 900 megawatts.
3NEXI covers commercial risks at 97.5% for 21 years.
4Trial operations for the first 300 megawatts begin in January 2028, and full commercial operations begin in September 2028.

Shokeir Wind Energy’s consortium announced on November 13 the financial close of a 900-megawatt wind farm near Ras Ghareb on the Gulf of Suez, moving the project into the financed implementation phase. The joint financing totals about $588 million, according to the Japan Bank for International Cooperation (JBIC), which said on November 12 that its contribution to the loan would reach about $285 million. Orascom Construction said the financing is based on non-recourse debt, meaning repayment is tied to the project company, its assets and its cash flows under the deal structure. The consortium will develop, own and operate the plant, while the project company will sell electricity to the Egyptian Electricity Transmission Company under a 25-year power purchase agreement. The financial close places the project, whose construction began in June 2026, among the renewable energy projects under way in Egypt.

Ownership of the project company is divided among ENGIE, with a 35% stake; Aeolus, with 40%; and Orascom Construction, with 25%, according to an Orascom statement. The ownership split reflects the three companies’ participation in the build-own-operate project, while the debt package brought together public, development and commercial financing institutions. The lenders include JBIC, Proparco, FMO, Société Générale, Crédit Agricole CIB and KfW IPEX-Bank. Nippon Export and Investment Insurance covers about $190 million in commercial loans, according to its November 12 announcement. The coverage provides a credit guarantee for a portion of the commercial financing within the structure that enabled the financial close.

NEXI’s policy covers commercial risks at 97.5%, with an insurance term of 21 years, according to the Japanese institution. The policy also includes 100% coverage for political risks, according to its published details. This is in addition to the Egyptian finance minister’s guarantee of the electricity purchase agreement, linking the financing to a long-term contract to sell the plant’s output to the Egyptian Electricity Transmission Company. The power purchase agreement runs for 25 years, longer than the stated term of the insurance policy. The structure thus combines electricity purchase revenue with coverage for commercial and political risks associated with the loans, according to NEXI disclosures.

The plant will have 86 turbines, each with a capacity of 10.5 megawatts, according to a Toyota Tsusho statement, bringing total nameplate capacity to 900 megawatts. Its expected annual output is equivalent to the consumption of about 2.2 million Egyptian households, the company said. The plant is also expected to reduce carbon dioxide emissions by about 1.5 million tonnes a year once operational. These figures illustrate the project’s scale and expected impact upon completion, while the financial close announcement did not specify a target for annual electricity generation. Egypt aims to raise renewables to 42% of installed power generation capacity by 2030, according to NEXI.

Construction began in June 2026, and the wind farm is expected to connect to the grid in three phases, according to Orascom Construction. Trial operations for the first 300 megawatts are scheduled to begin in January 2028, followed by full commercial operations in September 2028, according to Toyota Tsusho. The schedule follows ENGIE’s forecast in April 2026 that financial close would be completed by early in the third quarter of that year, with the first 300 megawatts operational in December 2027 and full operations in mid-2028. The subsequent announcement sets an updated date of September 2028 for full operations and puts the start of the first phase in January 2028. ENGIE said when it announced the project that it would be the company’s largest onshore wind farm globally, surpassing Brazil’s 846-megawatt Assuruá complex. Its senior executive vice president described the project as “another milestone for ENGIE in Egypt,” adding that it confirms the long-term confidence of its partners.