EL7.AI
StocksMedium•16 November 2026•
4 min read

BXDC Deal to Buy 75.1% of Two Amazon-Leased Data Center Projects Valued at $5 Billion

Key Facts

1BXDC agreed to acquire 75.1% of each joint venture, for a total value of $5.0 billion and an initial capitalization rate of 7.0%.
2The portfolio comprises 13 data centers with 647 megawatts of capacity, split between a 9-building campus in northern Indiana and a 4-building campus in Mississippi.
3Amazon will lease the entire portfolio; the weighted average initial lease term is 12 years, the extended term is 32 years, and annual rent increases by 2.75%.
4BXDC expects to contribute $1.9 billion from IPO proceeds and fund about $2.5 billion with nonrecourse mortgage loans.
5The deal is expected to close in the fourth quarter of 2026, with a right to terminate if it has not closed by December 31, 2026, and a $150 million termination fee in a specified case.

BXDC affiliates signed an agreement to acquire a controlling 75.1% stake in each of two joint ventures that own data center campuses, for a total value of $5.0 billion. According to the company’s filing with the U.S. Securities and Exchange Commission, the price reflects an initial capitalization rate of 7.0%. The deal would turn the assets into an income-generating investment for BXDC, as Amazon will lease the entire portfolio upon closing. The company’s chief executive and chairman said, "The quality of these assets, the deal fundamentals and the tenant profile make them a good fit for deploying our IPO proceeds." The deal is expected to close in the fourth quarter of 2026, subject to the agreement’s conditions being met.

The portfolio comprises 13 recently built data centers, with total information technology capacity of 647 megawatts. The campus in northern Indiana has 9 buildings, while the Mississippi campus consists of 4 buildings. The assets are thus spread across two U.S. sites, with all of the stated capacity concentrated in those campuses. According to its IPO statement, BXDC targets modern, income-generating and stable data centers leased to large investment-grade tenants under long-term contracts. The deal aligns with that strategy in terms of the assets’ age, the tenant’s identity and the length of the leases.

The agreement provides for Amazon to lease 100% of the portfolio under triple-net leases. The weighted average initial lease term is 12 years, rising to 32 years when all extensions are included. The contracts also provide for an annual rent increase of 2.75%. Amazon will retain a noncontrolling 24.9% stake in the joint ventures in exchange for transferring the properties to them. Amazon.com, the parent company, guarantees the tenant’s rent payment obligations, according to the filing.

BXDC expects to fund the deal with a $1.9 billion cash contribution from its IPO proceeds. The remaining amount required, including transaction costs, is expected to come from net proceeds of about $2.5 billion in new nonrecourse mortgage loans. The financing structure therefore combines IPO proceeds with property-backed borrowing, according to the figures in the filing. The IPO proceeds and loans are expected to fund the transaction at closing; the financing has not yet been completed. The next step depends on satisfying the deal and financing conditions within the expected timeframe.

The announcement came as Amazon’s cloud computing business posted accelerating growth. The company said in its third-quarter results, published on October 29, 2026, that AWS sales rose 39.3% year over year, its fastest growth in about five years. The business had an annualized revenue run rate of $184 billion in the quarter. Chief Executive Andy Jassy forecast AWS revenue growth of more than 40% in both 2027 and 2028, linking it to Amazon’s investments in infrastructure capacity. These figures place the expansion of infrastructure serving AWS in the context of the business’s growth, while the deal remains subject to closing conditions.

The deal also comes amid heavy capital spending on infrastructure tied to artificial intelligence. Amazon said its free cash flow was an outflow of $42.4 billion in the twelve months ended September 30, 2026, compared with an inflow of $14.8 billion in the year-earlier period, attributing the decline mainly to increased purchases of property and equipment related to AI investments. In the power market, the International Energy Agency said data center operators signed power purchase agreements for 45 terawatt-hours in the first half of 2026, up nearly 20% from the same period in 2025, with about 70% of the volume in the United States. The agency said the investment boom is putting pressure on local grids and electrical equipment supply chains, and that data center projects face grid capacity constraints, long connection queues and slow permitting processes. It also cited 134 policies and regulations worldwide aimed at guiding data center integration into power systems, with about 40% announced or implemented in the twelve months before the report.

The deal is scheduled to close in the fourth quarter of 2026, but remains conditional on meeting closing requirements. Either party may terminate the agreement if the deal has not closed by December 31, 2026, unless the deadline is extended under its terms. If either party terminates because the other party failed to close when required to do so, the non-breaching party is entitled to a $150 million termination fee. The filing identifies that fee as the non-breaching party’s exclusive remedy in that case. Until the deal closes, BXDC’s stake and the expected assets and leases remain contingent on the agreement’s conditions being met.

Open on chart