X-energy Completes Safety Review for 320-MWe Long Mott Project
Key Facts
X-energy said on October 30, 2026, that the U.S. Nuclear Regulatory Commission had issued the final safety evaluation for the Long Mott project in Texas, allowing the construction permit application to move into the final stages of review. The company said NRC staff concluded that the proposed plant and site provide a “safety basis for construction” under the regulatory framework of 10 CFR Part 50. Completion of the safety review does not mean the construction permit has been issued; the permit remains a subsequent step in the licensing process. The environmental review was completed in May 2026, completing the two main reviews required for consideration of the application. The development brings the project closer to a licensing decision, while the company’s investor materials continued to target permit issuance in the first quarter of 2027.
The proposed project at the Long Mott site comprises four Xe-100 high-temperature gas-cooled reactors. Their total capacity is 800 megawatts thermal, or 320 megawatts electric, according to World Nuclear News. Long Mott Energy, a wholly owned subsidiary of Dow Chemical, submitted the construction permit application in March 2025. The project aims to supply electricity and industrial steam to Dow’s operations at its Seadrift facility, with surplus electricity exported to the grid. According to the U.S. Department of Energy, the proposed reactors would replace aging power and steam generation assets at the site, which supports the manufacture of more than 4 billion pounds of chemical products annually.
X-energy said the NRC’s review covered the reactor’s key design criteria and preliminary design, safety analyses and probabilistic risk assessment, as well as research and development programs. The independent Advisory Committee on Reactor Safeguards also reviewed the agency staff’s assessment and endorsed issuance of the construction permit. The NRC held a mandatory hearing on the application on September 22, 2026, in Port Lavaca, where staff presented the environmental and safety reviews and opened the floor to public comments and questions. The company said its preliminary engagement with the agency dates to 2018. It added that the Xe-100 application is the first construction permit application for a high-temperature gas-cooled reactor to use the NRC’s technology-inclusive, risk-informed and performance-based framework.
The project is linked to the deployment of advanced reactors at an existing industrial site. The U.S. Department of Energy said it is supported by its Advanced Reactor Demonstration Program and would be the first advanced nuclear facility at an industrial site in the United States if approved. The Associated Press, citing Dow, estimated that the project could avoid about 500,000 metric tons of greenhouse gas emissions annually if built and operated as planned. X-energy says the Xe-100 design allows applicants to seek an emergency planning zone of 400 meters, compared with ten miles for conventional light-water reactors. That zone remains part of the company’s description of the design as the project undergoes licensing review by the agency. A construction permit, if issued, would also not authorize the units to operate; a separate application for operating licenses would have to be submitted in the future.
X-energy’s investor materials in May 2026 projected construction permit issuance by the first quarter of 2027, following completion of the environmental and safety reviews. The company said the NRC review findings could establish regulatory precedents for later Xe-100 projects, with each future application subject to a separate review. Proceeding with construction remains contingent on obtaining the permit and required approvals, as well as a decision by the company’s customers, including Dow, to execute the project. This means completion of the final safety evaluation marks an advanced stage of review, but does not settle the decision to build or operate the reactors. The project must complete the licensing process before the units can produce electricity and industrial steam.