Riot Sells 20,264 Bitcoin for $1.5 Billion to Fund Data Center Development

Key Facts

1Riot sold 20,264 bitcoin for proceeds of nearly $1.5 billion during the nine months ended September 30, 2026.
2The company held 2,418 bitcoin on September 30, 2026.
3Bitcoin mining revenue fell to $116.0 million in the third quarter of 2026, from $160.8 million a year earlier.
4The Corsicana contract covers 910 megawatts of capacity for an initial 15-year term, with a contractual value of approximately $28 billion.

Riot Platforms sold approximately 20,264 bitcoin for proceeds of nearly $1.5 billion during the nine months ended September 30, 2026, according to a filing with the U.S. Securities and Exchange Commission. Riot said the funds were used primarily to finance data center development and fully repay its $200 million Coinbase credit facility, without specifying how proceeds were divided between the two purposes. The sales reflect a strategy of funding expansion with assets produced by the company, alongside reducing its reliance on holding bitcoin. Riot ended the period with 2,418 bitcoin, after saying it expects to continue selling most of what it mines to fund development, projects, operating expenses and working capital. The company said bitcoin’s price decline and volatility during 2026 reduced the value of its production and holdings, forcing it to sell more than expected to fund operations and working capital.

The company had $950.2 million in cash and bitcoin on September 30, including $748.2 million in cash, which included $79.2 million in restricted cash, alongside bitcoin worth approximately $202 million. These figures provide a snapshot of available liquidity at quarter-end as the company continues to fund infrastructure projects. Mining activity, however, came under pressure from the decline in bitcoin’s price, with third-quarter revenue falling to $116.0 million from $160.8 million in the same period of 2025. Riot attributed the decline mainly to a fall in the average bitcoin price to $70,855 from $114,361 a year earlier. Bitcoin production rose 16% year over year, partially limiting the impact of lower prices on quarterly revenue.

For the first nine months of 2026, mining revenue fell to $341.6 million from $444.5 million in the corresponding period of 2025. The company said the average bitcoin price was $72,732 during the period, compared with $101,912 a year earlier, while production rose 7.7% year over year. Total third-quarter revenue, by contrast, was $181.4 million, up 1% from $180.2 million a year earlier. Riot attributed the overall stability to growth in data center and engineering revenue, which offset the decline in mining. Data center revenue was $18.4 million in the third quarter, reflecting leasing activity and tenant fit-out under the amended AMD contract; the company began reporting data center operations as a reportable segment in the first quarter of 2026.

On November 4, Riot announced an initial 15-year triple-net lease at its Corsicana campus covering 910 megawatts of IT capacity, with a contractual value of approximately $28 billion. The company said the lease with a leading AI lab became effective and binding on November 4, 2026, following board approval and the adoption by Riot Corsicana’s outside advisers of the site’s technical specifications. The contract is part of a broader expansion in data centers; together with the AMD contract and the Rockdale contract with the same lab, contracted capacity totals 1,151 megawatts, while contracted revenue is approximately $38 billion. Riot expects the portfolio to generate more than $2 billion in average annual net operating income once capacity is fully deployed. The company aims to build more stable contracted lease revenue and reduce its direct exposure to bitcoin price volatility.

Execution of the Corsicana contract spans three phases. Riot is targeting full commencement of phase one, with 400 megawatts of capacity, on September 11, 2027; phase two, with 200 megawatts, on January 28, 2028; and phase three, with 310 megawatts, on July 30, 2028. Phase one begins with its first block on June 28, 2027, while the company is targeting December 24, 2027, for the first block of phase two. For phase three, the target date for both the first block and the full phase is July 30, 2028. Rent is due for each block upon delivery, linking the start of revenue to actual phased delivery progress. Riot is responsible for building and delivering the power and site infrastructure, and for operating and maintaining the power infrastructure during the lease term, while the tenant is responsible for taxes, insurance, site expenses and electricity consumed.

The contract includes a provision allowing the tenant to terminate the relevant phase if it is not delivered within 270 days after its target date, provided it gives 30 days’ notice, with Riot granted cure rights and extensions for certain causes of delay. These terms make execution timing one of the factors that will determine how the announced contractual value translates into operating revenue. The chief executive estimated total capital requirements for the Corsicana project at approximately $5.5 billion. Riot said it does not currently expect to issue shares to fund the announced projects, citing lower capital requirements and a strong balance sheet. The company said it will allocate capital in the future to the use that delivers the greatest value per share, including business development or returning capital to shareholders, while its stock closed at $16.71 on November 6, 2026.