STT GDC Seeks $2.4 Billion Loan to Finance Its Assets

Key Facts

1STT GDC is in talks over a S$3.1 billion syndicated loan, equivalent to $2.4 billion.
2The proposed loan has a base tenor of 3 years and a margin of 165 basis points over SORA, with an option to extend by up to 2 years.
3Standard Chartered, United Overseas Bank, Oversea-Chinese Banking Corp. and DBS are participating in arranging the proposed financing.
4The company secured a ¥93 billion green loan to fit out and operate its TYO1 and TYO2 buildings.
5The company plans to develop 50 megawatts of new data center capacity in Singapore.

ST Telemedia Global Data Centres is in talks with banks about a S$3.1 billion syndicated loan, equivalent to $2.4 billion, according to a Bloomberg report cited by Investing.com on November 2, 2026. The proposed financing remains under negotiation, and the report did not say it had been signed or arrangements finalized. The report cited people familiar with the matter as saying the borrowing is intended to finance the company’s assets, without identifying the assets involved or how the proceeds would be allocated among them. The move comes as data center companies’ financing needs grow while technology companies expand the infrastructure required for artificial intelligence. The proposed loan’s size places the company within a broader wave of sector financing, while details on the use of proceeds remain subject to the outcome of the talks.

The report said Standard Chartered, United Overseas Bank, Oversea-Chinese Banking Corp. and DBS are working on arranging the financing. According to the report, the banks are participating as global coordinators, mandated lead arrangers and bookrunners. That means the banking group is taking on roles in coordinating and arranging the deal and marketing it to lenders, while the report does not name the ultimate lenders or specify the amount each bank has committed. The report did not say whether the company had set a date to close the financing or whether terms had been finalized with the banks. The deal remains, in the report’s description, proposed financing at the discussion stage.

Under the terms cited in the report, the loan would have a tenor of 3 years, with an interest margin of 165 basis points over the Singapore Overnight Rate Average, known as SORA. The proposal includes an option to extend the tenor by up to 2 years. These terms describe the reported borrowing structure but do not establish that the banks and the company have agreed to them definitively. The report also did not provide details on other fees, collateral or early repayment terms. Citing people familiar with the matter, the report said the borrowing is intended to finance STT GDC’s assets, without specifying whether it would cover capital expenditure, refinance existing obligations or a combination of the two.

The talks follow the completion in September 2026 of an acquisition of STT GDC by a consortium led by KKR and Singtel, according to an Investing.com report. A consortium of funds managed by KKR and Singtel had secured a S$5 billion sustainability-linked loan to support the acquisition, with DBS, Oversea-Chinese Banking Corp. and United Overseas Bank participating, according to an Aug. 31 announcement by United Overseas Bank. The announcement linked the pricing of that financing to targets including renewable energy use and the share of green data centers. That earlier financing was tied to the acquisition and is separate from the new syndicated loan under negotiation. The data center operator operates in 20 key markets across Asia-Pacific, the U.K. and Europe, according to United Overseas Bank data.

The company has previously announced separate financing arrangements and expansion projects in Asia. On October 27, it said it had secured a ¥93 billion green loan facility to fund the fit-out of its TYO1 and TYO2 buildings in Tokyo and their subsequent operation. It also announced in August that it had been selected to develop 50 megawatts of new data center capacity in Singapore for advanced computing and artificial intelligence workloads. The company said the proposed project would use liquid cooling and energy-efficient IT equipment, and that more than 50% of the center’s capacity was expected to operate through green-qualified energy pathways. It added that development of the center would proceed under the applicable approval and implementation processes, making the project subject to those processes as well as the company’s financing plans.

In Malaysia, STT GDC secured a green financing facility of up to $1.37 billion in August to support development of its Johor campus, planned for an IT load of up to 166 megawatts. These projects provide context for the company’s activity in developing and financing new capacity, but do not establish whether the proposed syndicated loan would be allocated to any of them. At the sector level, Investing.com cited Bloomberg data showing that the artificial intelligence boom has generated more than $650 billion in debt since the start of 2025. It also cited Moody’s Ratings’ expectation that data center-related investment would reach at least $3 trillion over the following 5 years. The report did not cite a market reaction to the talks, while the next disclosed step remains the completion of negotiations on the proposed financing.