Oracle Force Majeure Notice Puts Project Jupiter Power Risks in Focus

By

Key Facts

1A source told Reuters Oracle sent a force majeure notice concerning Project Jupiter over potential power delays.
2ORCL closed at $139.54 on September 24, 2026, versus $144.56 on September 23, according to EL7 data.
3Oracle says Project Jupiter remains on its planned schedule for 2028.

Oracle sent a force majeure notice to the developer of its Project Jupiter data center in New Mexico over potential delays in securing power, a person familiar with the matter told Reuters on September 24, 2026. ORCL closed that session at $139.54, down from $144.56 on September 23, according to EL7 data. The developer is a Blue Owl Capital unit, and Oracle is the site's main tenant. The notice addresses the possibility that the campus might miss its planned 2028 opening and the payments that could follow. Oracle says the project remains on its planned schedule, so the notice alone does not establish that opening will be delayed.

The two trading sessions put the report's timing in context. On September 23, 2026, ORCL traded between $144.23 and $148.66 before closing at $144.56, according to EL7 data. On September 24, it traded between $133.48 and $140.34 and closed at $139.54. The $144.56 price belongs to the session before the report, rather than to the market's response on publication day. The difference between the two closes captures the stock's entire move and cannot all be assigned to the project notice.

The notice matters because the tenant, developer and financiers have distinct obligations. The source told Reuters that Oracle is responsible for securing power for the site under the contract. Reuters, citing the Bloomberg report that first disclosed the matter, said Oracle seeks to defer payments if the campus fails to start operating in 2028 as planned. That is different from abandoning the project or ending the lease. Blue Owl said the notice does not change the parties' financial commitments to the project, an important limit on any assessment of its immediate financing impact.

The power risk is connected to a proposed natural gas pipeline serving Project Jupiter. New Mexico's State Land Office said it rejected a request in July 2026 to reconsider an earlier decision about a route across state land. The request covered a 0.6-mile segment of a proposed 17-mile pipeline. That decision concerns a right of way for that route and is not, by itself, a final decision on the whole campus. It does show why the timing of gas delivery matters when assessing when power could become available at the site.

A separate regulatory path concerns electricity generation on the campus. In a letter to New Mexico environmental authorities, Oracle urged approval of air permits for natural-gas microgrids at Project Jupiter. The company said those facilities would supply the site with electricity independently of the local grid if approved. Financing arrangements alone therefore cannot put the planned computing capacity into service; the infrastructure to generate and deliver electricity must also be ready. The outcome of the permit process, alongside the gas-supply route, remains directly relevant to the schedule Oracle says it can meet.

Those risks sit alongside rapid growth that Oracle has reported in its cloud business. The company recorded $19.3 billion of revenue in Q1 FY2027, up 30% from a year earlier. Cloud infrastructure revenue reached $7.4 billion, up 121%, while remaining performance obligations stood at $664 billion. Those obligations represent contracted work that has not all become revenue, making timely capacity delivery relevant to when demand can be recognized as sales. The results do not identify how much revenue depends specifically on Project Jupiter, so one site's risk should not be treated as a measure of every Oracle contract.

Oracle's funding program gives investors another reason to watch the construction timetable. The company said it sold $20 billion of common stock during Q1 FY2027 as part of its capital investment program. It also projected at least $90 billion of revenue for FY2027. The notice alone does not revise that guidance or establish a need for another share sale. It does sharpen a practical financial question: if infrastructure spending precedes the point at which a site can earn revenue for longer, the return on the capital committed to it also takes longer to arrive.

The issue also reaches the party financing development. A source told Reuters that Blue Owl has about $3 billion of equity in the project and earns a lower return during construction than it expects after completion. Under that account, delayed completion postpones the period of higher returns even if contractual commitments remain in place. The source also said Oracle bears the project's debt costs and cannot terminate the lease. The financial effect of force majeure thus depends on the payment timetable and allocation of costs, rather than on the notice's label alone.

For an ORCL holder, the central question is when contracted demand becomes operating capacity and revenue. A prospective buyer must weigh reported cloud infrastructure growth against the possibility of a longer spending period before this site starts service. A short seller, meanwhile, must distinguish a Project Jupiter risk from broader damage to Oracle's business that this event alone has not established. Those assessments turn on the length of any delay and who bears its cost, neither of which the reported notice settles. Later changes to the contract, schedule or financing would be more decisive than assuming the notice itself determines the outcome.

Attention now turns to the electricity permits and a resolution of the gas pipeline route, followed by the parties' ability to meet Project Jupiter's planned 2028 opening. Approvals and power delivery in time for operations would support Oracle's stated schedule. Extended deadlines or changed payment terms would increase the significance of delayed returns for the tenant, developer and financiers. Oracle's later disclosures on spending and cloud revenue will also help show whether capacity construction is keeping pace with the demand recorded in Q1 FY2027. Until those developments become clear, the notice identifies a contractual risk tied to power rather than a final outcome for the project.